How to tell a gutter is finished
Stand under the eaves in rain, or run a hose along the gutter on a dry day, and look for these:
- Rust perforation. Daylight through the base of the gutter, or rust blisters along the back where water has ponded. Once the steel has gone through, no sealant holds for long.
- Sagging between brackets. A belly that holds water after rain. Ponding water rusts the gutter from the inside, so a sag is the start of the next hole.
- Water over the front lip in moderate rain, with the gutters clean. That is a gutter or downpipe too small for the roof area feeding it.
- Staining and peeling paint on the fascia, or soft timber behind the gutter.
- Joins that drip. One or two can be resealed; a drip at every join means the gutter is at the end.
- Gutter pulling away from the fascia. The brackets, or the timber they are screwed to, have let go.
One leaking join or one dropped bracket is a repair, and we will say so. Rust through the base, or a sag along a whole run, is a replacement.
How we assess it
We walk the roofline and check every run for fall, bracket spacing and rust, then check the fascia with a screwdriver: soft timber behind the gutter needs dealing with before a new gutter goes on it. We count downpipes, measure the roof catchment feeding each one, and look at where the stormwater actually goes. On a lot of older Sydney homes the downpipe stops at a splash block, which is why the garden bed under it is a swamp.
You get a written quote on the spot with the metres, profile, colour, downpipes and any fascia work itemised.
Profiles and materials
Quad gutter is the D-shaped profile on most Sydney houses since the 1950s. It comes in 115 mm and 150 mm; we use the 150 mm on a large roof area or a steep pitch. Slotted quad has overflow slots in the front face so that when it blocks, water spills forward rather than back into the eaves.
Half round gutter is the profile on Federation, Victorian and interwar homes, hung on external brackets off the fascia. It looks right on a heritage house in Hunters Hill, Burwood or Balmain, and in a conservation area council may require it. It costs more per metre and takes longer.
Squareline and slimline are the flat-fronted profiles on newer homes and most Hills District builds.
Box gutter is the internal gutter behind a parapet or between two roof planes, on terraces, Art Deco blocks and commercial buildings. Different job entirely: it needs sumps, overflows and a rainhead, and it is sized from the catchment rather than picked from a catalogue. Commercial box gutter work is under commercial roofing.
For material, Colorbond steel is the default: pre-painted, 22 colours, a BlueScope warranty of up to 36 years depending on where you live. Zincalume is the same steel unpainted, cheaper and fine on sheds. Copper is for heritage work and lasts longer than any of us. Within a few hundred metres of surf we specify Colorbond Ultra, or the standard product rusts at the cut edges inside ten years. Colours are in Colorbond colours for Sydney homes.
Sizing to AS/NZS 3500.3
AS/NZS 3500.3 governs roof drainage in Australia. It sets the gutter cross-section and the number and size of downpipes from the roof catchment area, the pitch and the local rainfall intensity. The most common reason a new gutter overflows is that it was fitted with the same downpipes as the old one because that was easier.
Downpipe sizing is the part that gets skipped. As a working rule, a 90 mm round or 100 x 50 mm rectangular downpipe handles about 12 lineal metres of standard gutter on a normal pitch. A long run fed by one downpipe at the far end will overflow no matter how good the gutter is. We add downpipes where the maths says to, where they can reach a stormwater connection.
The standard also requires an overflow path: if the downpipe blocks, water must escape away from the building. Slotted gutter, a gap behind the gutter back, or overflow spouts on a box gutter all do this. A gutter fixed hard against the fascia with no overflow is how a blocked downpipe ends up as a wet ceiling.
The job, step by step
- Remove the old gutter and downpipes. We cut the brackets, drop the gutter in sections and load it straight onto the trailer.
- Inspect the fascia. Sound timber is fine to fix to. Soft or rotten sections are cut out and replaced, or the whole run is capped with a Colorbond fascia cover, folded steel that wraps the timber so it never needs painting again. Fascia cover is priced per metre on top.
- Set out the fall. Brackets at no more than 900 mm spacing, closer at corners and joins, set to a fall of at least 1 in 500 toward each downpipe. No fall ponds; too much looks wrong from the street.
- Hang the gutter. Runs cut to length on site, joined with riveted and sealed laps facing away from the flow, with stop ends and mitres at the corners. Outlets are punched and popped, not cut with snips.
- Downpipes and stormwater connection. New downpipes in Colorbond or PVC, fixed with astragals and connected into the existing stormwater pipe or pit. Work below ground is a plumber's job, and we say so.
- Hose test. Water into every section, checked for ponding and drips at the joins.
- Clean up. Offcuts and swarf cleared, ground magnet-swept for screws.
A single-storey home with 40 to 60 lineal metres of gutter is a one-day job. Two-storey homes need edge protection and run two days. Heritage half round on a big Federation roof can take three.
What it costs
Colorbond gutter supplied and installed, including removing the old, starts from $45 per lineal metre on most Sydney homes. Downpipes are from $180 each. Fascia cover is extra per metre. A typical single-storey house comes to a few thousand dollars; two storeys, half round, copper or extensive fascia repair push it well beyond that. Every quote is free, written and measured on-site.
When replacement is the wrong fix
- One join dripping: reseal it.
- One bracket let go and a short sag: re-bracket that section.
- Overflowing in heavy rain with gutters full of leaves: clean them first. If it overflows clean, then it is sizing.
- Gutters fine but constantly full: gutter guard rather than new gutters.
- A roof at the end of its life: replace the roof and gutters together. New gutters under a rusted metal roof will be pulled off again when the roof goes.
Warranty
Our 2-year workmanship warranty covers the fall, the joins, the brackets and the downpipe connections. The Colorbond coating carries its own BlueScope warranty, registered to your address. We work across Sydney from Gladesville, with most gutter replacement in the Inner West, the North Shore and Western Sydney. Book a free on-site quote and we will measure it properly.